Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Process Loads

CS-2009 EAp2:Minimum Energy Performance
posted by  Rodrigo Vazquez  on 

We are working on a project in Mexico City, to comply with the prerequisite 2 we are following Option 1, whole building energy simulation. In the first simulation we´d done of the energy model we c

1
Tue May 27, 2014, 4:11 pm

Occupancy Sensors for 'Back of House' space

CS-2009 EAp2:Minimum Energy Performance
posted by  Laura Charlier  on 

As it relates to occupancy sensors being installed in all 'back of house' spaces for this credit, what encompasses back of house spaces? Is there a comprehensive list? i.e.

1
Tue May 27, 2014, 4:16 pm

DEMAND RESPONSE energy modeling

NC-v4 EAc2:Optimize energy performance
posted by   Habitech Distretto Tecnologico Trentino  on 

How is it possible to take advantage of energy use reduction due to DR systems in EAp2-EAc1 energy modeling? Is there any reference guide or document as those for the "key cards" for example?

1
Tue May 27, 2014, 4:19 pm

Outdoor air delivery monitoring

NC-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Rodrigo Vazquez  on 

If the project is a core & shell design and the distribution of the area is not know (tenants space) yet, is it correct to specify only a CO2 sensor on the return duct of the AHU?

1
Mon May 26, 2014, 6:46 pm

SRI Testing Labs, Do They Need to be Certified in some way?

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Erin D.  on 

For users who are not using a roofing material with a known SRI, or for manufacturers who want to add SRI data to their product data sheets, does the lab they send their samples to need to be certi

1
Sat Jul 26, 2014, 6:09 am

NYC project

CS-2009 SSp1:Construction Activity Pollution Prevention
posted by  Megan Bove  on 

Hi. I have a project in the city where subway grates are found right outside the project fence as well as always a storm drain that is on a very busy street.

1
Tue May 27, 2014, 3:42 pm

Contained Contaminated Soils & non-ASTM E1527-05 Phase II

NC-2009 SSc3:Brownfield Redevelopment
posted by  Dana Murdoch  on 

We have a site with contaminated soils. A Phase II was conducted, but not per ASTM E1527-05 as required.

1
Tue May 27, 2014, 10:08 pm

EA Cr5: Measurement & Verification for projects wherein Option D

NC-2009 EAc5:Measurement and Verification
posted by  Sasha Peters  on 

The query is with reference to achieving EA Cr5: Measurement & Verification for projects wherein Option D and Option B of IPMVP Vol.III is not possible. In lieu of same, please confirm if in

1
Wed May 28, 2014, 1:55 pm

Does Seeding Apply

NC-2009 WEc1:Water Efficient Landscaping
posted by  Terry King  on 

Does seeding (hydroseeding) apply toward the needed 5% landscaped area? Thanks

1
Sat Jul 26, 2014, 6:08 am

LEED Boaundary and Utility Connections

Schools-2009 PIf4:Schedule and Overview Documents
posted by  Larry Turbes  on 

We're certifying a school addition and the site area associated is fairly straight forward except we have both power and sanitary utility connections that finger out beyond what would be a reasonab

1
Tue Nov 24, 2015, 8:09 pm