clarification question on credit
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Melissa Elkins on
Our Engineering firm didn't include our water heating system in the original commissioning report, so our credit needs to be clarified - they did conduct a functional test so I'm wondering if I jus
Disinterested Sub-contractor of MEP Design Firm?
NC-2009 EAc3:Enhanced Commissioningposted by Anthea Ng on
Hello. For achieving EA C3 Enhanced Commissioning, Wwe noted the clause in guidebook "Must not be an employee of the design firm, though he or she may be contracted through them".
Ventilation - Proposed and Baseline per ASHRAE 62.1-2007?
NC-2009 EAp2:Minimum Energy Performanceposted by Todd Tewksbury on
Hi! I am conducting a LEED v2009 EAp2/c1 energy model for a nonresidential building that is more than 5 floors.
Expansion project FLUSH OUT
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Jorge Torres-Coto on
We have a project that is an expansion to an existing facility. It is NOT an addition.
Multi zone or 100%OA ?
NC-2009 IEQp1:Minimum IAQ Performanceposted by SW LEE on
Our project is use VRF system to keep the space cool. We also provide dedicated injection fan (DOAS) as to meet 62.1 requirement. Most space will have indoor cassette unit.
Increasing the indoor operative temperature
NC-2009 IEQc7.1:Thermal Comfort—Designposted by Stella Stella on
Hi, we are doing a project in South east Asia for LEED NC.
Off-Site Parking
NC-2009 PIf2:Project Summary Detailsposted by Mary Kay on
My project is new construction - a hangar at an airport that will be used for painting jet airplanes. The owner already has previously built a building adjacent to our site with a parking lot.
Freight and tax on wood invoices
NC-2009 MRc7:Certified Woodposted by Renee Shirey on
The wood invoices that I have show a separate line item for tax/fuel charge/freight charges, etc. and I was unclear how to include this in the documentation.
EBOM 2009 EAp1 L-9 upload document
EBOM-2009 EAp1:Energy Efficiency Best Management Practicesposted by James Doyle on
The credit template form for EBOM 2009 EAp1 on page 2 requests "Upload L-9. Provide a breakdown of total project building annual energy consumption by major end uses or applications.
How to document split system units
NC-2009 EAp3:Fundamental Refrigerant Managementposted by Helene Lefkowitz on
I am working on a hotel project that has multiple split system units. This means two part numbers, one for each unit, to account for all mechanical cooling equipment.