Baseline system in ASHRAE 90.1 G3.1.1
NC-v4 EAp2:Minimum energy performanceposted by Eric Dyer on
Hello,
I have a question in the process of creating a baseline system in our modelling.
Our project is in System8.
LEED baseline model with proposed increased ventilation and pressurization
NC-v4.1 EAp2:Minimum Energy Performanceposted by Moses Chong on
Has any one worked on LEED project that includes increased ventilation credit AND the project has an pressurization-based ventilation rate? What should I do with the baseline model?
Fire and Police Station Building Type Use
NC-v4.1 LTc7:Reduced Parking Footprintposted by Danielle Waters on
I saw on LEEDuser v4 NC LTc7 that Fire Stations could be "General Light Industrial" (1.85/1000 sf), but is it far fetched to consider "Other Public Assembly" (0.25*permitted capacity) if the commun
Police Headquaters and Public Services Building
NC-v4 LTc7:Reduced parking footprintposted by Marlene Borruso on
I am currently working on a Police Headquarters and Public Services Building.
Should we track quantity and costs for profiles and caps/wall base moldings ?
NC-v4.1 EQc2:Low-Emitting Materialsposted by Priscillia Champagne on
I am wondering if edging profiles (like Schluter systems let's say) as well as wall base caps and moldings (like Tarkett finishing accessories) need to be tracked for the Flooring Category.
Parking garage with 2 sides of 6 sides 50% open to the outside
NC-v4 EQp1:Minimum indoor air quality performanceposted by Paola Moschini on
Table 6.4 of ASHRAE 60.1-2010 Note C states that for parking garages exhaust not required if two or more sides comprise walls that are at least 50% open to the outside.
Pre-cast concrete structure environmental product declarations
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Maiz Rech on
Considering the building is built of a precast concrete structure that was made of steel and cement and those present environmental procuct declarations, may I use these EPDs to comply wi
Which buildings/structures to consider while registering project
EBOM-v4.1 MPR2:Must use reasonable LEED boundariesposted by Wafa Arif on
I have three office towers on one large property, each connected to a mall via walkways. The shared parking structures beneath these towers serve tenants, mall visitors, and others.
Basement carpark areas?
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Scott McMillan on