On-site and off-site renewable energy
Data-Centers-NC-v4.1 EAc5:Renewable Energyposted by Urban Green on
A new data center will be constructed in a university campus.
1
Fri Sep 22, 2023, 3:21 pm
Water Analysis - (Maximum concentration exceed 10)
NC-v4 WEc3:Cooling tower water useposted by Osman Faroq on
Dear All,
0
Porch lighting included in building energy model?
NC-v4.1 EAc2:Optimize Energy Performanceposted by Rachel Novick on
Our building has a large open-air porch that we use for parties. It has lights and ceiling fans.
1
Fri Sep 22, 2023, 3:22 pm
Outdoor Air Delivery Monitoring in Warehouse
Warehouses-NC-v4 EQp1:Minimum indoor air quality performanceposted by Gopinath Vasu on
Hi All,
3
Wed Sep 20, 2023, 9:05 pm
Exclude common roads that serve multiple buildings?
NC-v4.1 SSc5:Heat Island Reductionposted by Maureen Drullard on
I am curious what folks make of this statement from the "step-by-step guidance" in the v4.1 Beta guide: "Common roads that serve multiple buildings should not be included in this calculation.
2
Wed Sep 20, 2023, 5:11 pm
Telecommute Option in Arc Transportation Survey
EBOM-v4.1 LTp1:Transportation Performanceposted by on
Hello all,
1
Mon Jun 24, 2024, 12:50 pm
Cutsheet of Btu meter for chilled water metering
CI-v4 EAc3:Advanced energy meteringposted by Nagaraj Sankar on
Credit - Advanced Energy Metering
1
Wed Sep 20, 2023, 1:02 pm
v4.1 July 2023 Guide - EAC Arbitrage
NC-v4.1 EAc5:Renewable Energyposted by Christina Hohman on
The newest v4.1 Guide (July 2023) has added the following language - "Note that while the previous versions of LEED allowed for EAC arbitrage for on-site systems, LEED v4.1 requires the owner to re
1
Fri Sep 22, 2023, 3:28 pm
Inherently non emitting sources
NC-v4.1 EQc2:Low-Emitting Materialsposted by Subhashkumar A on
The project consists of ceramic tile flooring and precast concrete ceiling panels in some areas. According to LEED standards, these products are inherently non-emitting sources.
2
Tue Sep 19, 2023, 5:14 pm
Offsite renewable energy production
NC-v4.1 EAc5:Renewable Energyposted by Subhashkumar A on
The project is planning to achieve renewable energy credits through offsite solar and wind power generation.
1
Tue Sep 19, 2023, 5:24 pm