Which buildings/structures to consider while registering project
EBOM-v4.1 MPR2:Must use reasonable LEED boundariesposted by Wafa Arif on
I have three office towers on one large property, each connected to a mall via walkways. The shared parking structures beneath these towers serve tenants, mall visitors, and others.
Basement carpark areas?
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Scott McMillan on
As noted above the requirement is applicable to "All adhesives and sealants used onsite within the weather barrier".
Want to consider 30% fresh air in printing areas
CI-v4 EQp1:Minimum indoor air quality performanceposted by Nagaraj Sankar on
DES Owned by A Third Party
NC-v4 EAp4:Fundamental refrigerant managementposted by Candice Rogers on
Hello -
Waste-to-Energy diversion
NC-v4.1 MRp2:Construction and Demolition Waste Managementposted by Danielle Waters on
In LEED v4, waste-to-energy was addressed, but for LEED v4.1 it is not clearly stated.
Definitions for a lab/office building
NC-v4 LTc7:Reduced parking footprintposted by Maiz Rech on
Hello!
TABLE 1. Default Occupancy Numbers
CS-v4 EQp1:Minimum indoor air quality performanceposted by Oscar Martinez on
Hi, I'm working on a warehouse project in Mexico. The rating system is v4 CS and I have a question in progress.
Advanced metering for cooling and ventilation
NC-v4 EAc3:Advanced energy meteringposted by Dina El-Sady on
How can we separate metering for cooling an ventilation if they are both within the same unit ?
Menstrual product dispensors
Pilot-Credits WEpc147:All-Gender Restroomsposted by Emily Smith on
The biggest hurdle we faced integrating this credit into our project was the requirement regarding providing free menstrual products.
Rainwater Management
NC-v4 SSc4:Rainwater managementposted by Ribert Senzoga on
I am evaluating the Rainwater Management of a warehouse project where the water table is very high and we don't have enough depth to make a water basin.