V3 project Minimum Indoor Air Quality Performance Pre-requisite.

CI-2009 IEQp1:Minimum IAQ Performance
posted by  sajjad Malik  on 

I have submitted minimum indoor air quality performance pre-requisite for final design review and reviewer ask me for a narrative but I do not find any option for upload the narrative or any option

1
Thu Jul 20, 2017, 5:28 pm

Different work week lengths

EBOM-v4 LTc1:Alternative transportation
posted by  Claire Bannister  on 

Our facility has office staff who work Monday-Friday, and production staff who work Monday-Thursday...

1
Tue Sep 12, 2017, 12:39 am

FSC calculations - weight or volume?

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Julie Hardy  on 

Good afternoon everyone, We are wondering if the FSC contribution should be calculated, as in LEED 2009, by volume or weight for products.

1
Mon Aug 28, 2017, 2:38 pm

Do individual storage facilities count as long-term storage?

Mid-Rise-v4 LTc2:Site selection
posted by  Tim Nabholz  on 

I have a project that has 69 dwelling units and provides indoor bicycle storage for 39 bikes. The project also includes storage lockers in the underground garage for each unit.

1
Tue Jan 22, 2019, 6:28 pm

Parking Ventilation

CS-2009 IEQp1:Minimum IAQ Performance
posted by  Praveenbabu Rajkumar  on 

We are working on IT/ITES project with above grade parking floors which are naturally ventilated.

0

Ireland Climate Zone

NC-v4 EAp2:Minimum energy performance
posted by  James Duggan  on 

Hi all, Could anyone clarify if Ireland is in climate zone 5A or 5C? Thanks in advance

1
Thu Jul 20, 2017, 2:08 pm

Ireland Climate Zone

CS-v4 EAp2:Minimum energy performance
posted by  James Duggan  on 

Hi all, Is Ireland Climate Zone 5A or 5C?

1
Thu Jul 20, 2017, 2:06 pm

Lighting Levels

CI-v4 EQc6:Interior lighting
posted by  Kristopher Croghan  on 

For the three levels of lighting, what about an overhead light, and a task light. Technically that is three different levels when both the task and overhead lights are on. Thoughts?

1
Tue Sep 5, 2017, 10:11 pm

EA Credit 1 Optimise Energy Performance - reaching criteria

CI-2009 IDc1:Innovation in Design
posted by  Anna Brodersen  on 

Right now our project for an office building is en route to meeting the criteria of the updated LEED 2009 EA Credit 1 for optimising energy performance.

1
Mon Jul 24, 2017, 3:04 pm

Thermal controls for 50% occupants

CI-v4 EQc5:Thermal comfort
posted by  Gabriela Mena   on 

Hi, We have a project in Mexico City, the system is VRF and for the interior spaces we have Fan coil units, approximately 60% of the project area is open office space and it is complicated to pro

1
Tue Aug 8, 2017, 4:40 pm