NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Akira Kataoka on
I understand that USGBC are seeking feedbacks from stakeholders on the draft EPD guidance. When is the final version scheduled to be ready and when would the guidance become effective?
Residential Switched Receptacles
NC-2009 IEQc6.1:Controllability of Systems—Lightingposted by Alexis Thompson on
To satisfy credit requirements should we provide the corresponding light fixtures for switched receptacles in residential units in a multi-family high-rise project?
On-site waste water treatment
NC-v4 WEc2:Indoor water use reductionposted by Lorne Mlotek on
In LEED 2009 there was a credit dedicated for reducing waste water or treating it on site. How does LEED V4 reward onsite treatment?
Achieving Innovation Design: MRc2 (95%)
NC-2009 MRc2:Construction Waste Managementposted by James Goldfield on
Hello Everyone, I am currently on a project where one of our goals is to achieve Innovation Design: MRc2 Exemplary Performance (95%).
CWM Campus Credit
NC-2009 MRc2:Construction Waste Managementposted by ethen mcmanus on
My project is composed of 10 buildings on a college campus. I know for a fact the CWM credit is a campus credit. How do I document this? Do i go to each building on LEEDONLINE and upload?
Multiple Street Frontages
Pilot-Credits PC14:Walkable Streetsposted by Carrie Webster on
Our project is on a corner and has two street frontages, with the primary façade on the "main street" and one side along a side street.
Energy Recovery Bypass
NC-2009 EAp2:Minimum Energy Performanceposted by Kalyan Nishtala on
Hi, I am working on a building which includes DOAS units with energy recovery cores on the proposed systems. The baseline systems do not require energy recovery per ASHRAE 90.1-2007.
RWH Pond outside LEED Boundary
NC-2009 PIf4:Schedule and Overview Documentsposted by ABDUL MUTHALIB MOHAMED on
Our project building is located in a campus and it is registered individually. Rainwater harvesting pond is located in the campus but it is outside the LEED Boundary.
Building Envelope Cx Checklist for LEED Documentation
NC-v4 EAc1:Enhanced commissioningposted by Joyce Kelly on
I am currently developing a Building Envelope Cx Checklist for LEED v3 projects.
OPTION 2. ENVELOPE COMMISSIONING (2 POINTS)
NC-v4 EAc1:Enhanced commissioningposted by Ciaran McCabe on
Can anyone identify the range of Building Envelope seasonal tests that are required to satisfy Option 2. Is there a typical list of activities outlined by LEED.