Project Building Activity - Residence Hall
NC-2009 PIf3:Occupant and Usage Dataposted by Anna Lapomme on
I'm currently working on a project in Jersey City for a University that is building a new residence hall.
Equipment not list on CPG
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Maria Isabel Conde on
Our project has a WSHP bigger than 135000 btu/h. According to CPG table 2.9.2 the efficiency required for WSHP up to 135000 btu/h is 14 EER and the WSHP of our project has a 14.1 EER.
Campus approach
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Febin Mohamed on
' LEED will accept the establishment of a permanent private shuttle bus to a place where there is direct access to rail or two or more bus lines' Can this be applied to a project going for Multip
Untenanted spaces with no lease agreements
CS-2009 IEQp1:Minimum IAQ Performanceposted by John Mader on
We have a question about retail tenant spaces inside an office building.
ASHRAE requirements for dry-coolers
CS-2009 EAp2:Minimum Energy Performanceposted by Agnieszka Rylska on
Cooling system in our project (shopping mall) consists of dry-coolers sprayed with water. What are ASHRAE efficiency requirements for dry-coolers?
Structure and enclosure
Schools-NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Allison Zuchman on
One of the most impactful changes to this credit from LEEDv3 is: "Structure and enclosure materials may not constitute more than 30% of the value of compliant building products." In my experience s
Signed Contract with the CxA
NC-2009 EAc3:Enhanced Commissioningposted by Mohamed M. Abd Elhameed on
We are pursuing LEED Certification for a 476921.20 sq ft Mixed Use Office Building in Egypt.
Option 1: Calculated Water
EBOM-v4 WEp1:Indoor water use reductionposted by Ileana Delgado on
I am working on WE prerequisite for Indoor water use reduction and we decided to go with the 1st option.
Minimum Energy Performance
EBOM-v4 EAp2:Minimum energy performanceposted by Aqrab Ali Rana on
Dear All, I am working on a industrial project registered in Existing building Operation and maintenance located Out of US , that have its own electricity production of 4 Mw through gas engines a