Forum quick links
MSDS with expiration date?
NC-2009 MRc4:Recycled Contentposted by Marcio Alberto Casado Pereira on
Hi folks, We've been receiveing Material Safety Data Sheets informing VOC levels, recicled content percentage and distances for MRc5 with expiration date and this seems to be common practice by ma
Interpreting CIR#1712
NC-2009 EAp2:Minimum Energy Performanceposted by Yoyo Shek on
Dear All, I have a question in modelling the lighting power density for high-rise residential development.
Metal/Wood Furniture to contribute to FSC credit?
CI-2009 MRc7:Certified Woodposted by Ward Miller on
We've found the project owner's preferred furniture for this fit-out. Many of the pieces are made of mixed materials that have metal and other non-wood parts for legs, arm rests, etc.
Process Loads
CS-2009 EAp2:Minimum Energy Performanceposted by Paula Hernandez on
Hi, I know this has been discused before, but I still can´t make it. The thing is that I have a C&S building to model. I have assumed 35 W/m2 of other loads on all tennant spaces, which the sim
Examples of pre-consumer recycled content exclusions
CI-2009 MRc4:Recycled Contentposted by Michelle Lambert on
The given definition of "pre-consumer" recycled content per LEED is "material diverted from the waste stream during a manufacturing process.
Tandem parking
CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Gabriela Hernández Castillo on
If we provide tandem parking within our building (tandem spaces will be used for valet parking), should we leave these out of the total spaces? I mean, lets say I have 50 regular spaces and 50 tan
French VOC labeling rule
CI-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by soha yamani on
I have an HDF that is which have the following emissions level of TVOC (class valid for the French VOC labeling rule) : Class A Does that make it comply for this credit ?
MERV-8 Filtration
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Marcia Weekes on
I was under the impression that every LEED project would need to demonstrate use of MERV 8 filtration during construction due to the fact that building commissioning is a prerequisite of LEED and s
"Push button" instead of "Occupancy sensor"
NC-2009 EAp2:Minimum Energy Performanceposted by Maya Karkour on
Dear All, To benefit from a lighting power reduction, our project is proposing installing push-button switches in the communal stairs. I know that in ASHRAE Appendix G, table G3.2 allows for a 10%
Connection to Existing Building
Schools-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Eri Spaulding on
Credit requirements seem to indicate that 10' long compliant mats are to be located at all "regularly used exterior entrances".