Case 2 Calculator

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Peter Keithly  on 

We had to use the Case 2 calculator because our building was too small to qualify for an Energy Star rating.

2
Default Avatar
Principal
TEAM Commissioning Associates
LEEDuser Basic Member
3 thumbs up
Wed May 9, 2012, 12:06 am

Tenant's Access to BMS Room

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Maya Karkour  on 

Dear all, We're developing an M&V Plan for a large commercial mall.

3
Default Avatar
Project Engineer
Integral Group
LEEDuser Basic Member
23 thumbs up
Tue May 8, 2012, 10:13 pm

White polyethylene SRI

NC-2009 SSc7.1:Heat Island Effect—Non-Roof
posted by  Guillermo T. Adamo  on 

Hi, We are pursuing the credit by covering 50% of the parking places with a white polyethylene shade cloth of 70% density.

3
Tue May 8, 2012, 8:32 pm

Timing of IAQ testing compliance

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Anders Olson  on 

I am part of a LEED NC 2009 for Retail project that intends to pursue Option 2 -- Air Quality Testing -- for this credit.

4
Sustainability Manager
Clark Builders
LEEDuser Premium Member
8 thumbs up
Tue May 8, 2012, 8:17 pm

Flushout calcs for Option 1 Path 1

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Mark Haynie  on 

To achieve the required time needed for flush out, do we only take into consideration the OA louver volume (CFM)?

2
Default Avatar
CIH, LEED AP, CBCP
CIH Environmental Solutions
LEEDuser Basic Member
3 thumbs up
Tue May 8, 2012, 3:47 pm

EAc1 ASHRAE 90.1-2007 Energy Simulation Model

NC-2009 EAc1:Optimize Energy Performance
posted by  Denise Newbould  on 

Can someone tell me how difficult this modeling software is to use, and how long would it take an engineer who isn’t already familiar with it to get up to speed?

7
Tue May 8, 2012, 2:24 pm

IEQp1 - Occupant diversity

NC-2009 IEQp1:Minimum IAQ Performance
posted by  susan eguia  on 

Hi, We have existing Library project with combined multiple zone and single zone.

11
Default Avatar
LEED Coordinator/Construction Administrator/Business Development
Building Solutions Group, Inc.
LEEDuser Basic Member
47 thumbs up
Mon May 7, 2012, 10:04 pm

Duct Work

CI-2009 MRc3.1:Materials Reuse
posted by  Holly Himes  on 

I think I know the answer, but can duct work be counted towards material re-use?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon May 7, 2012, 8:26 pm

Why IEQc5 Applies to Entire Building?

CI-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Andrew Gil  on 

No disputing that the requirements of IEQc5 are both sensible and valuable,, so much so that our firm now incorporates these provisions in ALL projects, regardless of LEED certification intent.

5
Director - Green Building Advisory
Colliers International Ltd.
LEEDuser Basic Member
201 thumbs up
Mon May 7, 2012, 6:26 am

Bird Collision Deterrence

Pilot-Credits SSpc55:Bird collision deterrence
posted by  Trinidee Shelton  on 

Our team is attempting this credit and it appears that the bird threat rating calculation does not include any type of tools to determine the threat of an angled glass which was designed to reflect

4
Fri May 4, 2012, 6:16 am