Forum quick links
Defining space types
CI-v4.1 EQc9:Acoustic Performanceposted by Rachel Bundy on
Would you include a restroom adjacency as an occupied space? If so, how would you define it as private?
Fans as an End Use
NC-v4 EAc3:Advanced energy meteringposted by Pooja Sannamani on
Hi, we'd like to make sure we are meeting the intent of the credit correctly when it comes to fans.
Cubicle Hardware Included in Low-Emitting Materials Credit
NC-v4.1 EQc2:Low-Emitting Materialsposted by Nicole Jenkins on
While the language reference cubicle/curtain/partition walls, has anyone included cubicle hardware in the Low Emitting Walls/ Ceiling credit?
Experience with Pilot Credit MRpc87- Verified Construction & Demolition Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Sam Mitchell on
The overall intent of the pilot is definitely impactful in helping to shift the market to more strict verification processes; however, there could me more alternative compliance path
Separate buildings with common basement
NC-v4 EAp2:Minimum energy performanceposted by Nikos Tsitsikas on
Hi all,
PBT Source Reduction Calculator sill required for all LED lighting?
Healthcare-v4 MRp3:PBT source reduction - mercuryposted by Rebecca Mann on
Our healthcare project is a new build, and will specify all LED light fixtures. No fixtures contain mercury.
Need more info on v4.1 Integrative Process credit
NC-v4.1 IPc1:Integrative Processposted by Victoria Rios Esteve on
Hi everyone! We are working on the certificacion of a major renovation building. We are willing to get this IP credit but have some doubts.
Building façades as urban landmarks
Hospitality-NC-v4.1 EQc8:Quality Viewsposted by Ricardo Sá on
Hi,
Experience Feedback for Biophilic Design
Pilot-Credits EQpc123:Designing with Nature, Biophilic Design for the Indoor Environmentposted by Robyn Vettraino on
In our experience with this pilot, it was really the intent that stood out as the driving force behind the design decisions and there was less of a need to simply check boxes of pre-set requirement
Safety First: Re-Enter Your Workspace COVID-19
EBOM-v4 INc1:Innovationposted by ERM Korea on
Has anyone achieve the credit Safety First: Re-Enter Your Workspace