LEED Interpretation 10231 still valid for v4?

NC-v4 SSc2:Site development - protect or restore habitat
posted by  CT G  on 

LEED Interpretation 10231 required a vegetated roof to be an intensive roof system, where the depth of the growing medium is 6 inches or more, and with at least six varieties of sedu

1
Tue May 29, 2018, 5:26 pm

Install electric chargers by phases

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Instra Ingenieros  on 

We are pursuing in this credit the "Option 2: Providing onsite alternative fueling stations for 3% of total vehicle parking capacity is a bit more involved and potentially more expensive.

6
Sustainable Design Leader
HKS, Inc.
LEEDuser Premium Member
40 thumbs up
Thu May 24, 2018, 3:35 pm

Manage Runoff from Entire Site Requirement

NC-v4 SSc4:Rainwater management
posted by  Karina Lairet  on 

Per the USGBC Guide, it says that the project must manage rainwater runoff from the entire site within the project boundary.

1
Thu May 24, 2018, 3:11 pm

Gender Neutral toilets

NC-v4 WEp2:Indoor water use reduction
posted by  Jude Chakraborty  on 

Hello, we are working on an University project which has a directive on Gender Neutral toilets  which means there are no urinals in the building.

5
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Wed May 23, 2018, 11:15 pm

Room Geometry Adjustment - Baseline Lighting Power Increase

NC-v4 EAp2:Minimum energy performance
posted by  Luis Andrade  on 

Hi,

When modeling the Baseline's lighting power using the Space-by-Space method, may I icrease the Baseline's power by section 9.6.3 (Room Geometry Adjustment) by 20% ( if applicable)?

1
Thu May 24, 2018, 1:44 pm

metal door in factory-finished metal product exception?

NC-v4 EQc2:Low emitting materials
posted by  Charline SEYTIER  on 

Hello,

We have a question concerning the exception in Wall and ceiling categories on 'factory-finished metal product':  

11
Sustainability Project Manager
Atkins
LEEDuser Basic Member
59 thumbs up
Wed May 23, 2018, 4:23 pm

photocatalytic air cleaning surfaces

NC-v4 INc1:Innovation
posted by  Henrik Sarfelt  on 

Is there a possibility that photocatalytic surfaces will give LEED points?

2
Design Engineer
LEEDuser Expert
19 thumbs up
Wed May 23, 2018, 2:30 pm

Excluding reuglarly occupied areas

CS-v4 EQc4:Daylight
posted by  Jens Apel  on 

I know there is a must in the rating system variations; but is there any chance in C&S to exclude areas that are defined as regularly occupied?