EAp2-c1 ACP
CS-v4 EAp2:Minimum energy performanceposted by Vassil Vassilev on
Greetings,
While performing EAp2 for a C&S registered project, could we apply the ACP spreadsheet calculator as we did in CS 2009.
Thanks.
Regularly Occupied Area - Kitchen Countertops and Islands
NC-2009 PIf3:Occupant and Usage Dataposted by Rose Winter on
I know that residential kitchens are considered regularly occupied.
Facade lighting - off after 10pm
NC-2009 SSc8:Light Pollution Reductionposted by Anna Korinkova on
Hello, Would that be possible to reach the credit, if the facade lighting doesn't fullfil the upligth criteria, but it is turned off after 10pm?
Elevators with regenerative braking - EAp2 form
CS-2009 EAp2:Minimum Energy Performanceposted by Pamela Svetllana Santos Souza on
Hello, We are modelling for LEED C&S 2009. The project has 26 floor type of mixed-use offices. My question is about the Minimum Energy Perfomance credit form (EAp2).
guestrooms keycard: power adjustment for automatic lighting ctrl
NC-2009 EAc1:Optimize Energy Performanceposted by Habitech Distretto Tecnologico Trentino on
This project is a hotel: guestrooms are provided with keycards, so when guestrooms are not occupied all lighting fixtures are automatically shut-off.
Seeking expert opinion relating to a legal case
CI-2009 IEQc8.1:Daylight and Views—Daylightposted by Ellen Fox on
I don't know if this is the appropriate forum for this question but I don't know where else to ask my question and I also thought it might be of interest to this group.
Performance Period
EBOM-2009 IEQc1.2:IAQ Best Management Practices—Outdoor Air Delivery Monitoringposted by Summer Minchew on
The LEEDonline form for this credit indicates that installation of outdoor airflow measurement device, summary report/maintenance plan and trend graph from at least one outdoor airflow measurement
Appointment of CxA for Enhanced Commissioning
NC-2009 EAc3:Enhanced Commissioningposted by kerry wang on
My project is about to complete the Design Development stage and CxA is to be on-board soon.
Annual financial support - for how many years?
EBOM-v4 SSc1:Site Development- protect or restore habitatposted by Ameet AA on
Hi,
The option 2 financial support must be made annually, but the client clearly wouldn't want to be obliged forever. Can the client specify a minimum number of years in the agreement?
Integrative Process for Health Promotion
NC-v4 INc1:Innovationposted by Brian Salazar on
I am working with a healthcare company on a new facility.