Advertisements in Exterior Lighting

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings,

We are modeling a KFC fast food restaurant.

As everybody is aware there are illuminated advertisement in the outdoor walls and some ad signs on the roof.

1
Wed Jan 17, 2018, 3:50 pm

Plan Views

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Dinesh V  on 

Is there a minimum horizontal distance from the glazing/window to meet the requirements of this credit?

 

1
Thu Jan 18, 2018, 12:49 pm

Case 1, Option 2 baseline

EBOM-2009 WEc3:Water Efficient Landscaping
posted by  Ryan Tinus  on 

Hi, I am attempting to calculate the baseline for irrigation, and came across an EPA Watersense Water Budget tool that can be used to determine the water efficiency of landscaping.

8
Tue Jan 16, 2018, 9:56 pm

Clarification on LEEDv4 Low-Emitting Materials credit

NC-v4 EQc2:Low emitting materials
posted by  Jason Grant  on 

In the IEQ: Low-Emitting Materials credit, under the heading Emissions and Content Requirements, section on General emissions evaluation, it says that “building products must be tested and determin

12
Default Avatar
Sustainable Design Director
Bell Architects
LEEDuser Premium Member
41 thumbs up
Tue Jan 16, 2018, 9:51 pm

Amtrak and Megabus

NC-v4 LTc5:Access to quality transit
posted by  Sara Zoumbaris  on 

Our project is shy of the second weekend trip threshold (108) by 1-ride. We are within walking distance of Amtrak, which has regularly scheduled pickups at our location twice a day.

5
Tue Jan 16, 2018, 6:37 pm

What transit type is the Subway (underground) System?

CI-v4 LTc3:Access to quality transit
posted by  Olga Yuil  on 

What transit type is the Subway (underground) System?

Is it light rail, heavy rail or commuter rail?

6
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Tue Jan 16, 2018, 6:35 pm

Existing building curtainwall reduced glazing %

NC-v4 EAp2:Minimum energy performance
posted by  Wade Cooper  on 

I have an existing envelope that is a complete curtain wall assembly that is to be replaced.  The overall WWR for the building is over 70% currently and is being removed and redesigned to

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jan 16, 2018, 4:06 pm

Option 1: which software shall we use??

NC-v4 EQc7:Daylight
posted by  Ricardo Sá  on 

Hi,

 

we're experiencing lots of difficulties to correctly assess this credit. Some notes:

5
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Tue Jan 16, 2018, 3:48 pm

% of Herbs required

Pilot-Credits SSpc82:Local food production
posted by  Francesco Passerini  on 

Hello, we want to pursue this credit, but we have a doubt. Under all project description says "Herbs used for food preparation shall not exceed 25% of the area requirement.

1
Mon Jan 15, 2018, 3:35 pm

Gross area v. net area in PI Form 3 and IEQ8.1

NC-2009 PIf3:Occupant and Usage Data
posted by  James Bell  on 

PI Form 3 requires gross area of Occupied Space.

5
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Mon Jan 15, 2018, 10:20 am