Demand Response Program available but building can't meet requirements

NC-v4 EAc4:Demand response
posted by  Jason Garvens  on 

Can a project still be eligible to apply for the single point for Case 2 if the project's utility does offer a DR program but the project doesn't sign up for it due to the requi

1
Thu Jan 11, 2018, 6:04 pm

Management of on site runoff at a neighboring retention pond

NC-v4 SSc4:Rainwater management
posted by  Jason Garvens  on 

I'm working on a project being built in a designated industrial park area.

1
Thu Jan 11, 2018, 6:49 pm

Externally illuminated building signage

NC-v4 SSc6:Light pollution reduction
posted by  Gordon Wong  on 

I have a project in Auburn, CA for the California Conservation Corp.  The new building will have a stem mounted luminaire that will illuminate the building name.  Since this luminiar

3
Thu Jan 11, 2018, 2:04 pm

Roof Top Patio

NC-v4 SSc5:Heat island reduction
posted by  Irene Chung  on 

Hello, 1/4 of my project's roof area is going to be patio that is accessible to occupants. Can rooftop patio be excluded?

5
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Thu Jan 11, 2018, 12:31 pm

Track Energy Consumption data

EBOM-v4 EAp3:Building-level energy metering
posted by  Ana Paula Quiros  on 

According to the guide:

Track energy use monthly, beginning at least 12 months before the final day of the building’s initial LEED
O+M performance period.

1
Tue Jan 16, 2018, 10:29 pm

Retrofit of a existing building into green building

EBOM-2009 WEc1:Water Performance Measurement
posted by  Mohammed Ibrahim  on 
How i can calculate the use of water in a college building?
6
Editorial Director
BuildingGreen, Inc.
LEEDuser Expert
159 thumbs up
Wed Jan 10, 2018, 5:45 pm

Storm water from neighboring site

NC-v4 SSc4:Rainwater management
posted by  Bradley Magnusson  on 

The project I am working on is in a campus setting and the neighboring site's excess runoff is discharged into a storm drain pipe that runs through our project's

1
Wed Jan 10, 2018, 6:01 pm

NC-v4 SSc2 - Site development - protect or restore habitat

NC-v4 SSc2:Site development - protect or restore habitat
posted by  Mar Mulero  on 

Hello :an outside area of land with vegetation, but where lighting has been installed and dirt roads have been formed, long time ago, it can be considered a greenfield area or previously disturbed?

1
Thu Jan 11, 2018, 11:54 pm