Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Threat Factor Calculation

Pilot-Credits SSpc55:Bird collision deterrence
posted by  Francesco Passerini  on 

Hi I've been working on a project where I want to purse this pilot credit.

1
Thu Jan 11, 2018, 2:52 pm

Monitoring-based commissioning

NC-v4 EAc1:Enhanced commissioning
posted by  Paula Rantanen  on 

In our project building, we have many measurement points that do not measure energy consumption directly but the energy consumption can be reliably calculated from the tracked data and the building

1
Wed Jan 10, 2018, 3:22 pm

Which flow rates to use?

NC-v4 WEp2:Indoor water use reduction
posted by  Nate Tsang  on 

Hi all, The prerequisite lists the baseline flow rates at 60psi (415 kPa). Does this mean that the proposed flow rate must also be at 60psi?

5
Sustainability Consultant
Stantec
LEEDuser Premium Member
13 thumbs up
Wed Jan 10, 2018, 2:20 am

Solid Untreated Wood Window Sills

NC-v4 EQc2:Low emitting materials
posted by  Alara Brinton  on 

We have a project installing solid wood, (untreated) for the window sills & some baseboards.

11
Wed Jan 10, 2018, 12:01 am

Signage at Equipment Rooms with Exterior-Only Access

NC-v4 EQp2:Environmental tobacco smoke control
posted by  Stephanie Graham  on 

My project is a fleet maintenance garage with storage.  Per prerequisite requirements we are providing the no-smoking signage at all building openings including intakes, overhead doors and oth

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Tue Jan 9, 2018, 5:51 pm
1
Tue Jan 9, 2018, 6:04 pm
1
Fri Jan 12, 2018, 12:37 am