Car and motorcycle parkings
CS-v4 LTc7:Reduced parking footprintposted by Emmanuel Pauwels on
For this credit, are motorcycle parkings spaces also included or only car parking?
Energy modeling- DOAS units with reactivation air
NC-2009 EAc1:Optimize Energy Performanceposted by Matt Hollenbeck on
I have an HVAC system that will use a DOAS unit to supply neutral temperature air in a humid climate (climate zone 2). The proposed DOAS unit utilizes a dessicant wheel with reactivation
Fundamental Commissioning Timeline
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Todd Bundren on
I am working on a project where the Owner Project Requirements and Basis of Design were created at the appropriate times.
Can a project earn points under both options?
NC-v4 LTc4:Surrounding density and diverse usesposted by Elizabeth Cagle on
I'm a newbie to LEED, and although this seems like a simple question, I haven't been able to find the answer with the resources I have available.
Bi-polar ionization
CI-v4 EQc1:Enhanced indoor air quality strategiesposted by Suchi Daniels on
Universities and Colleges in Florida have installed bi-polar ionization for multiple purposes. First, improved energy efficiency, second improved indoor air quality, and third, reduced mainte
No Appliances in the Scope
Hospitality-NC-v4 WEc2:Indoor water use reductionposted by Muge Karasahin on
Hello,
We are currently working on a pod hotel project, where there no laundry or food services within the hotel.Therefore there are no appliances included in the project.
Water Metering (prereq and credit)
Warehouses-NC-v4 WEc4:Water meteringposted by Ryan McEvoy on
If a project installs one meter for the building (essentially collectively metering indoor plumbing fixtures and domestic hot water) and another meter for irrigation water, what are the ramificatio
Membrane roof - materials at interior side of vapor barrier?
NC-v4 EQc2:Low emitting materialsposted by Joanna Switzer on
Hi all,
Constuction Waste plan for Option 2
CI-v4 MRp2:Construction and demolition waste management planningposted by Deborah Stadler on
If a contractor is opting for Option 2 under the Construction and Demolition Waste Management credit, (less that 2.5 lbs/sf) do they still need to plan for Option 1 indicating the 5 streams to obta