EAc3 Exemplary Performance
CS-2009 EAc3:Enhanced Commissioningposted by BH . on
Thanks for all descriptions and comments related to differences beween EAp1 and EAc3. I`m still confused about Exemplary Performance and it`s "comprehensive envelope commissioning".
CO2 sensor issue
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by G B on
Hello all, I would kindly ask for an information please. My HVAC multizone system, looks like this. VAV AHU system (with sensible heat recovery, no mixing) + Fan Coil Units (FCU).
Time line for PV installation
CS-2009 EAc2:On-site Renewable Energyposted by Sayeed Muhammad on
In our project we intend to install PV panels for 300KWp capacity. Its a NC2009 project aiming for LEED platinum. The building is office building with a 24hrs cafeteria.
question about set of fan power in simulation program
NC-2009 EAp2:Minimum Energy Performanceposted by lin wang on
The fan power calculated by the formula presented in APPENDIX G3.1.2.9 of ASHREA90.1-2007 is the sum of all the fan power including supply fan,returen fan,exaust/relief fan.
Free materials
CI-2009 MRc4:Recycled Contentposted by Martin O'Donnell on
Hi our company has moved to a new office and we are submitting for LEED gold.
Alternative Transporation for an inn.
EBOM-2009 SSc4:Alternative Commuting Transportationposted by Nana Simopoulos on
We have an inn that is seeking LEED certification. Our innkeeper lives in the building. Because we are in the center of a small town, we walk to the post office, bank and grocery store.
Finish Grading, Seeding and Plantings - applicable for MRc5?
NC-2009 MRc5:Regional Materialsposted by Renee Shirey on
In the Resource book on page 383 and 385 I see tables that have "plant material" as one of the regional items, but I am confused by the language in the actual credit - "BUILDING materials or produc
FTE for residential project Case 3 of LEED CS
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Paola Figueiredo, Newton Figueiredo on
I have a question to calculate the FTE for a residential project (2 towers in one condominium of one building).
Transportation Canopies
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Aliesa Adelman on
We have a project where caopies at an intermodal station are considered a roof system by code yet are not attached to the facility and do not fall under the LEED definition of a roof.
How to model slab-on-grade floor in simulation program
NC-2009 EAp2:Minimum Energy Performanceposted by lin wang on
As ASHREA90.1-2007 shown,the slab-on-grade floor of baseline building shoud be modeled by the parameter of F-factor.But the parameter to model slab-on-grade floor in program eQuest is U-value or pr