EAp2 Equipment Motors

CI-2009 EAp2:Minimum Energy Performance
posted by  Eric Claycamp  on 

For a LEED CI project that includes a fitness center, do you count the motors in the treadmills and cross trainers? No fitness equipment I have found is Energy Star rated.

1
Wed Mar 23, 2011, 9:09 pm

Using as ID credit in New Construction, indoor & outdoor

EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lamps
posted by  Sarah Corbitt  on 

I'm working on a project which is using this credit as an ID credit for LEED-NC. Must outdoor lights be included?

1
Tue Mar 29, 2011, 1:26 am

EAc1 required 2 points

CI-2009 EAp2:Minimum Energy Performance
posted by  Jennifer Berthelot-Jelovic  on 

I know that for EAc1 there was a requirement that "All LEED for New Construction project registered after June 26, 2007 are required to achieve at least two (2) points." Since I am working on a LEE

1
Wed Mar 23, 2011, 9:05 pm

LEEDuser plumbing assessment template updated

EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by  Tristan Roberts  on 

To all LEEDuser members using our Water Efficiency Economic Assessment Policy for WEp1: we have made a couple minor updates to it to improve it relative

1
Wed Jun 22, 2011, 8:27 pm
1
Tue Mar 29, 2011, 1:35 am

Design Engineer Signatory

CI-2009 EAp2:Minimum Energy Performance
posted by  Sundararaj Subburaman  on 

Please let me know if the HVAC Designer will be representing the Design Engineer Signatory for the EA P2? If not who will be the Design Engineer - MEP designer?

1
Wed Mar 23, 2011, 9:00 pm

5 star Energy Star House

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  John Kinch  on 

Hello again, Our facility is already a 5 star energy rated building. Is there any way to cut corners on this paperwork? Thanks!

1
Tue Mar 29, 2011, 4:52 am

Innovative water efficiency

EBOM-2009 IOc1:Innovation in Operations
posted by  Melissa Merryweather  on 

A project considering LEED EBOM is looking to add a new rainwater catchment system because it will be lower-cost then replacing old sanitary ware.

1
Thu Mar 24, 2011, 11:58 am

Multi-parameter alternative product analysis

Pilot-Credits PC2:PBT Source Reduction: Dioxins and Halogenated Organic Compounds
posted by  Jeff Gearhart  on 

We are pursuing this credit for a CI project. Interested in any further guidance on "multi-parameter alternative product analysis".

1
Fri Apr 1, 2011, 7:18 pm

Guadua

NC-2009 MRc6:Rapidly Renewable Materials
posted by  Carlos Alberto Hoyos Soto  on 

I want to know if anyone has use guadua, and if it is considered as rapidly renewable material, thanks.

1
Thu Mar 24, 2011, 3:30 pm