Annual building energy determination
Schools-2009 EAc2:On-Site Renewable Energyposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on
Does this credit require the sum of ALL energy uses (electricity, gas, etc.) for the proposed building be the basis for determining the renewable energy percentage or is it just the electricity use
RP Credit Without a Threshold/Path
EBOM-2009 RPc1:Regional Priorityposted by Phillip Saieg on
The list of RP Credits for our project (zip code 80202) includes SSc6.
green power - purchased percentage
CI-2009 EAc4:Green Powerposted by Andy Plogsted on
Our client owns the building and occupies 50% of the square footage of a singularly metered building. The owner (our client) signed a contract to purchase green power for 30% of the total building
Off Site Parking
CI-2009 SSc3.3:Alternative Transportation—Parking Availabilityposted by Jeff Mosher on
Can one acheive this credit via compliance path B. (no parking) if the facility has no on-site parking, but does have an off-site parking lot with a shuttle service?
Residential Units with Natural Ventilation
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Sustainability Provider on
Hello, I have two questions: 1) We have a residential multi-unit project with approximately 100 units. All the individual units are naturally ventilated with openable windows. (ie.
Permanent entryway walk-off systems at least 10 feet long
Schools-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Gendel Metlitsky on
Q #1: We are working on design of 10-story school in downtown of the major US city. Design calls for roof play yard.
T(vis) as a %
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Brynn Horley on
LEED (Canada) is requiring minimum T(vis) of 0.4 A manufacturer has provided me information which says that their product is 33% Visible Transmittance.
VOC Excluding Exempt and Including Exempt
CI-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Alan Bernstein on
I have two products that were used on our project. A primer and paint. The cut sheets from Manufacturer state the VOC Content is: Excluding Exempt: 275g/l and the Including Exempt is 103 g/l.
Operable Windows
CS-2009 IEQp1:Minimum IAQ Performanceposted by Luis Miguel Diazgranados on
We are working on a natural ventilated CS office building. The Leedonline form asks to fill in a table with the operable window area, in order to calculate ratio of window to occupiable area.
Baseline and design system selection
NC-2009 EAp2:Minimum Energy Performanceposted by Bala Srini on
Our semi industrial building's production area does not have cooling system, Proposed model simulated based on ASHRAE 90.1-2007, Table G3.1, 10. HVAC No.