Overlapping
EBOM-2009 IOc3:Documenting sustainable building cost impactsposted by Hatice G. on
Can the performance period overlap the historical year? Or should the historical years end before the performance period starts?
Regional Materials
Schools-2009 MRc5:Regional Materialsposted by Rebecca Griffith on
When calculating distance between the manufacturing plant & the project site, is the distance I should use, actual travel distance by land, or by "how the crow flies"?
LEED for Retail: Qualifying for Option 4 (Parking Capacity)
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by John Klein on
LEED for Retail Option 4 Path 1 states "size parking capacity must meet but not exceed minimum local zoning requirements".
Open plan (individual workstations) with access to thermostat
NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfortposted by Karen Stewart on
We have an open plan office area that contains 24 workstations. There are 3 thermostats that control the temperature in this open office plan area.
Grouping of spaces
CS-2009 IEQp1:Minimum IAQ Performanceposted by Anupam Jain on
I am working on a project with similar spaces repeating on each floor. I know LEED allows one to group spaces in some credits.
Can a PC count for Campus?
Pilot-Credits PC41:Wastewater Managementposted by Prudence Ferreira on
If we were to certify a campus EBOM project and we pursued this credit for a campus wastewater treatment facility would this PC gain a point for each building that used the wastewater treatment cen
AASHE STARS / Climate Action Plan - Master Site Innovation
NC-2009 IDc1:Innovation in Designposted by M. Elbaum on
Any thoughts if an AASHE STARS rating for a college campus will earn you a Master Site Innovation credit? What about being an ACUPCC signatory and having a Climate Action Plan? These would be two
Weighted average for new construction + major renovation?
NC-2009 EAc1:Optimize Energy Performanceposted by Bethany Beers on
We are performing a review of an energy model for a project that is a major remodel of an existing space with addition of new square footage.
A & B bus lines - do they count separately?
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Jill Ziegler on
We are going for Exemplary Performance since we have 5 qualifying bus lines. Total (weekday) stops equals exactly 200, so we're good there.
Phase I for an Existing School
Schools-2009 SSp2:Environmental Site Assessmentposted by John McFarland on
Do we need a formal Phase I assessment for a school remodeling project (major renovation)? The school site was a greenfield site when it was originally constructed approximately 50 years ago.