Forum quick links
Exempt area of 10% in a Group Project
posted by Gabriel Frasson on
We have a site that contains two buildings that are being certificate as a campus project. In the ground floor of Tower A there are some stores that we want to exempt of the certification project (
IEQ c4.2 Paints - Laboratory tests according to SCAQMD Rule#1113
Schools-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Andrea Tayah Esperão Malta de Campos on
In a LEED 2009 CS project in Brazil and a Epoxi Paint was used in a parking garage.
VRP Compliance Calculator or 62MZCalc for projects outside U.S.?
NC-2009 IEQp1:Minimum IAQ Performanceposted by Geraldo Pithon on
I am submitting for review a project outside the US, in Brazil. The legislation of Brazil is very similar to that specified by ASHRAE 62.1.
Calculation
NC-v4 EAc7:Green power and carbon offsetsposted by Vitor Tosetto on
Dear All, I have a doubt about calculation of quantity of REC. I believe you can help me. Using the Example 1 (in page 460 of v4) my project will consume 1,98 MWh per year.
VRF system
NC-2009 EAp3:Fundamental Refrigerant Managementposted by GISELA FARHAT DE ARAUJO on
We are using the vrf system on a project. Should i put as type of equipment Split AC or should i chose the "others" option?
Dist. Center - Light polution
Warehouses-NC-v4 SSc6:Light pollution reductionposted by Antonio Macedo Filho on
If the design of a distribution center worked 24 hours in 3 shifts, even at night, could we not get that credit? If we use external lighting with zone presence sensors would not it be possible?
Zone Calculation Ds% for VAV System
NC-2009 IEQp1:Minimum IAQ Performanceposted by Marina Andrade on
I received this question in IEQp1: "The ventilation calculations indicate that the value of the flow rate of air projected under the condition tested (DS) was modeled as 100% level for each of th
Alarm to closed openings
NC-v4 EQp1:Minimum indoor air quality performanceposted by Vitor Tosetto on
Dears, When we have a Naturally Ventilated Space, we can use an alarm to indicate that the openings are close. Someone know if I can use an light alarm? or I must use an sound alarm?
Footfall Vibration on HC
Healthcare-v2009 IEQc2:Acoustic environmentposted by Saymon Grauppe on
Hello. There's another doubt now about Footfall Vibration . It will be used a rubberized coating that reduces this effect and also has sound absorptive properties.
2012 EPA CGP comply with this prerequisite?
CS-2009 SSp1:Construction Activity Pollution Preventionposted by Pamela Svetllana Santos Souza on
I'm modelling for LEED C&S 2009 and the project has 26 floor type of mixed-use offices. Does the 2012 EPA CGP can be used instead of 2003 EPA CGP to comply with this prerequisite?