Forum quick links
ID Credit for CSv 2009 Project
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by José Solis on
Is it possible to use this credit as an ID credit for a CS v2009 project? Could we achieve it if we write the requirements into the tenant lease language or the binding tenant requirements?
Workspace opens to exterior and interior
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Peter Doo on
We have a project that includes a workshop/studio space.
Credit Still Open?
Pilot-Credits PC12:Reduced Automobile Dependenceposted by Rachel Bannon-Godfrey on
Hello! We are interested to pursue option 1 and are using LEEDv4. Is this credit still open for registration? Thanks!
Can We Use Both Facility and Site Rates?
NC-2009 MRc2:Construction Waste Managementposted by Sara Zoumbaris on
Hi all, I am working on a project that ended up using 2 separate waste haulers during the time of the project - one for the first half or so, and the second for the remainder of the project.
Green-E Equivalency
EBOM-2009 EAc4:On-Site and Off-Site Renewable Energyposted by David Ellner on
We have pursued EAc4, using a combination of on site and off site renewable energy sources. On site sources is not a problem.
Construction - Indoor Air Quality V2009
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Noelle Hunner on
Does the indoor air quality credit allow for propane powered lifts (inside the building) during construction? Or do they have to be battery powered only?
Is touch-up paint exempt?
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Erin Holdenried on
This LEED Interpretation states that touch-up paint consists of small unanticipated quantities that can't be controlled by specifications, and therefore is exempt from the credit.
Views exculsion for High Bay Window areas
Schools-2009 IEQc8.2:Daylight and Views—Viewsposted by David Sundersingh on
We are in the early stages of design for a Career Compact Center, this has 3 workshop areas with high bay windows for natural lighting.
Project has all 5 Categories
Schools-2009 WEc4:Process water use reductionposted by Sara Zoumbaris on
Hi all, My project has all 5 categories installed (dishwasher with racks, pre rinse etc..), however one of the products is above the maximum limit.
Annual Energy Cost
NC-2009 EAc2:On-Site Renewable Energyposted by Sarah Thompson on
I am trying to figure out which cost to put in here. Another post said it was savings, although I can't find anything under the credit intent or resources for this specific item.