Fueling Capacity - multiple stations

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Garrett Ferguson  on 

In regards to the number of fueling stations, we have a charger that can charge 2 cars simultaneously (one plug on either side), and can reach 2 spots in either direction with a long cord.

1
Wed Apr 22, 2015, 3:31 pm

IEQ4.1 Aerosol Adhesives conversion

Schools-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Kevin Taterus  on 

Using IEQc4.1 template version 4.0, in the notes under table IEQc4.1-1, the note #1 states "in the case of aerosol adhesives, the project team must provide a conversion of both the product VOC cont

1
Wed Oct 12, 2016, 3:11 pm

green cleaning

CS-2009 IDc1:Innovation in Design
posted by  Alfonzo Collins  on 

Realizing I should have posted this here...I received a comment on a design phase review that since this is a core & shell building, the owner has to either include green cleaning in the lease,

1
Sat Aug 26, 2017, 10:54 pm

Precertification - LEED 2009 Core & Shell

CS-2009 SSp1:Construction Activity Pollution Prevention
posted by  Michael Heacock  on 

We are working on submitting a precertification. I'd thought the credits team was working on were design phase. If I submit the precertification, can I quickly turn in for design phase.

0

Asbestos Abatement Requirement Compliance

NC-2009 SSc3:Brownfield Redevelopment
posted by  UO Design and Construction  on 

We always conduct asbestos surveys (assessments) in accordance with the LRAPA regulations Title 43.

1
Wed Mar 9, 2016, 3:58 pm

IEQ c4.3 Flooring

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Rezkar Abdulmajeed  on 

We have a project with some floor areas designed to be ceramic and quarry tiles. Can someone advise if the two above need to meet floorscore standrads. your comments are appreciated

1
Thu Feb 12, 2015, 2:06 pm

Multiple indentical RTUs combined with plenum ducts

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Chanyang Shin  on 

Multiple identical RTUs combined with plenum ducts serve a whole building. How can I prepare 62.1 MZcal? Can I add up cfm of all RTUs and assume it like one system using one sheet?

1
Thu Aug 18, 2016, 8:13 pm

Application Guide for Campuses and Multiple Buildings

General forums
posted by  Jeff Smitley  on 

Is there an Application Guide for Campuses and Multiple Buildings that can be used for LEED v4 BD+C: Schools?

1
Wed Feb 18, 2015, 2:19 am

Regularily Occupied or not?

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Alex Barrera  on 

I'm working on an industrial building in Virginia. One of the rooms is a Quiet/Sleep room, where employees can rest in between their shifts.

1
Fri Jun 17, 2016, 12:29 pm

material streams

CI-v4 MRc6:Construction and demolition waste management
posted by  Sean Quinn  on 

We are working on a project where there is not enough room for on-site separation, and the commingled waste will be picked up by the sorting facility.

1
Fri Aug 18, 2017, 2:41 pm