Occupancy Counts differ from workstation count significantly
EBOM-2009 IEQc2.2:Controllability of Systems—Lightingposted by Vanessa Seibert on
I'm working on a 800,000 s.f. high rise building with 40 tenants.
Des Heating
CS-2009 EAp2:Minimum Energy Performanceposted by Lorey Flick on
I have 5 existing buildings on a campus that are served by a common (existing to remain) steam boiler plant. There are no other buildings served by this plant.
Pressure drop adjustment factor with DOAS System
CS-2009 EAc1:Optimize Energy Performanceposted by Curtis Clark on
In the proposed model, we have a HEPA 13 filter in a dedicated outdoor air unit which serves a variable refrigerant flow system.
sunset date for projects registered under LEEDv3
posted by Gail Napell on
has anyone heard of a required completion date for projects registered under v3?
Utility sells "Community Solar" in yearly blocks - NOT Green-e
NC-2009 EAc6:Green powerposted by Joyce Kelly on
The local Utility sells "Community Solar" in yearly blocks - is NOT yet Green-e certified but willing to provide all the data required to be Green-e certified.
Determining STC ratings for ceiling products
NC-v4 EQc9:Acoustic performanceposted by Adam Stoker on
The LEED v4 acoustics credit addresses sound isolation purely through composite STC ratings. In my research, I have struggled to find STC ratings for ceiling products.
What if landscaping isn't installed yet?
EBOM-2009 WEc3:Water Efficient Landscapingposted by Vanessa Seibert on
We are in the PP but do not have our low-water landscaping installed. A contract will be signed to install it prior to the end of the PP. Has anyone obtained the credit this way?
Need help, using new v2009v4_Minimum IAQ Calculator_v03
CI-2009 IEQp1:Minimum IAQ Performanceposted by Edgar Arevalo on
After adding all the values for four floors I'm working on, I then input the design OA intake flow for each floor's AHU. In the summary tab, 3 out of 4 of the Zone systems meet the required OA int
IAQ Testing
posted by Roland Jones on
I have been asked to provide IAQ Testing for LDP, and am having trouble finding the distinctions between the normal pre-occupancy sampling for credit 3.2 and the during occupancy sampling of LDP.
Customer Use of Restrooms
Retail-CI-v4 WEc1:Indoor water use reductionposted by Mélanie Pitre on
Working on a retail project, we have the same case as described by Donny Goris Kolb in his comment : the store's restrooms are intended for employee use, but employees are directed to grant custome