Minimum building energy performance
ND-Plan-v4 GIBp2:Minimum building energy performanceposted by sam Alfassy on
based on the fact that we are on a planning stage only, what would be the documentation that approves compliance to this requirement.
Occupant Default Density vs. Actual density
CS-2009 IEQp1:Minimum IAQ Performanceposted by Maya Karkour on
Hello, we are working on a C&S Mall project, is it permitted that we uncheck the Default density checkbox in IEQp1 form, and enter expected number of persons based on Architects / Engineers ex
Reuse of aggregates
EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumablesposted by Fareed Alghimlas on
The building our team is trying to get it LEED certified has originally a shallow swimming pool with stones and aggregates in it for decorative purposes, during the performance period, the buildin
Satisfaction rating
EBOM-2009 IEQc2.1:Occupant Comfort—Occupant Surveyposted by Fareed Alghimlas on
Is it acceptable to resort to a 5 point scale on the comfort survey instead of the 7 point?
smoke leakage test for duct
NC-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Abdulla Anwar on
Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test, prior to final air leakage test since the project specs is giving a small allowable 1% from basis of des
Baseline System 2
NC-2009 EAc1:Optimize Energy Performanceposted by SSN Energy Model on
As per Table 6.8.1D, I observed the following EER = 12.3-(0.213*Cap/1000) EER Also, Cap means the rated cooling capacity of the product in Btu/hr.
Exhaust fan for chemical storage
CI-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Yaser Al Sharif on
If We have chemical storage room with 69.4 ft square in Area in our building , i want to install one exhaust fan for this room to acheive credit requirements , how can i calculate minimum pressure
Proposed case outside airflow rates
NC-2009 EAp2:Minimum Energy Performanceposted by Cagril Comert on
Hi, Our office building is ventilated with a constant volume AHU and conditioned by VRF system. AHU supplies 100% fresh air to the spaces, while VRF system provides heating and cooling.
Temporary Materials - Formwork
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Christopher Drew on
The materials credits apply to components that are permanently installed in the building.
Campus approach in a gated residential compound or ND?
posted by ABDELHAMID BESHARA on
We have a gated Residential Compound consisting of around 60 buildings - 4 to 5 stories high - different models.