Forum quick links
CCHP System modeling
NC-2009 EAp2:Minimum Energy Performanceposted by Jie Shen on
My project is provided by CCHP system which owned by third party, the CCHP has two gas generators, one heat recovered gas absorption chiller, two normal chillers and two boilers.
Historic site
CS-v4 LTc3:High priority siteposted by Jie Xiong on
Hi I am new to V4. There is a question about this credit. On the RG, page 75 further explanation, says that "project may......indicates has significant historic or cultural value".
WEp1 and c1: Indoor Water Use Reduction
CI-v4 WEp1:Indoor water use reductionposted by BEE Incorporations on
Hi! We understand that all newly installed water fixtures must be WaterSense labeled.
Replace All Filtration Media
EBOM-2009 IEQc1.5:IAQ Best Management Practices—Facility Alterations and Additionsposted by Ran Zhang on
Hi I am working on a project located in Tokyo Japan. We are aiming to pursue IEQ c1.5 and thinking about the requirements regarding the filtration media replacement right now.
Flush out for 1 storey high bay warehouse
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Renaud Gay on
Hello, We have a 1 storey 30m high bay warehouse as a part of our project.
Building Footprint
CS-2009 SSc7.2:Heat Island Effect—Roofposted by Jaesik Lim on
Hi, all Our team had a technical advice from USGBC reviewer, the comment is like below... " The LEED form indicates a total roof area (excluding mechanical equipment, photovoltaic panels, and skyl
energy-saving target during construction
CS-2009 IDc1:Innovation in Designposted by Dee Yun on
Hi, I have a project that has energy-saving target during the construction phase.
parking area under cover
CI-2009 SSc3.3:Alternative Transportation—Parking Availabilityposted by ANNA SUN on
my Project is in Shanghai China.I am preparing PI Form form my project. Now I have a question about parking area.
When covering a wide range of products
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Akira Kataoka on
A company is planning to publish an EPD(s) for their gypsum board products.
Energy Star equipment
CI-2009 EAp2:Minimum Energy Performanceposted by mingyu Zhang on
Hi All: Our project is a little bit special, so i wonder whether we can get the scores of EAp2-4.