Green Power - Carbon Offset

CI-2009 EAc4:Green Power
posted by  Henry Mak  on 

Hi All, I am working on a project located in China.The owner is the local electric company who has solar power and wind power supply.

1
Wed Dec 2, 2015, 2:37 pm

unfinished space simulation

NC-2009 EAp2:Minimum Energy Performance
posted by  Hongyun Zhou  on 

My building has four floors, and 4th flr is left empty for future use.

1
Wed May 24, 2017, 4:07 pm

Improving thermal comfort for ski center and ice rink

NC-2009 IEQc7.1:Thermal Comfort—Design
posted by  Chen Jin  on 

I am dealing with a complex commercial center that contains a ski center and a ice rink, which clearly fall outside of the comfortable zone of ASHRAE 55.

0

Faucet Flowrate at Actual Water Supply Pressure

CI-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Ran Zhang  on 

Hi all, I have a question in regard to the flowrate of faucet, whether it should be based on the 60psi specified by LEED or local water supply pressure.

0

Documentation upload to LEED Online

CS-v4 EAc1:Enhanced commissioning
posted by  Erin Rowe  on 

We are just getting ready to submit LEED CI V4 commissioning documents, and I noticed that it only requests that we upload the table of contents for both the Final Cx Report and Ongoing Commissioni

1
Wed Aug 16, 2017, 12:28 am

Is there LEED CS Precertification plaque?

General forums
posted by  Wangsoo Lee  on 

Is there LEED CS Precertification plaque?

1
Wed Dec 30, 2015, 7:32 pm

DCV requirement for high-occupancy areas

CS-2009 EAp2:Minimum Energy Performance
posted by  Shenhao Li  on 

Hello! We have a canteen project in Shanghai. The building has three floors, total GFA is 64,067 square feet. The baseline HVAC system type is system 6.

1
Tue Apr 5, 2016, 2:48 pm

Question about ASE study area

NC-v4 EQc7:Daylight
posted by  Jackie Cheung  on 

Hello everyone. May I ask 2 questions about this credit? A) Assuming a project go for option 1.

9
Default Avatar
Associate
(no longer with WSP)
LEEDuser Basic Member
0 thumbs up
Wed Aug 30, 2017, 6:27 pm

Fixtures outside the project scope

CI-v4 WEc1:Indoor water use reduction
posted by  Takayuki Hirota  on 

Our office project will occupy two floors of a newly constructed building and the building owner will provide all water fixtures including water closets, lavatory faucets and kitchen faucets.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Aug 28, 2017, 1:32 am

Price of dwelling unit for sale

ND-v4 NPDc4:Housing types and affordability
posted by  Noriko Nagazumi  on 

We are trying to determine the price of affordable dwelling unit.

2