Recent

VENTILATION WAREHOUSES

Warehouses-EBOM-v4 EQp1:Minimum indoor air quality performance
posted by  Helena Garcia   on 

We are certifing a project with two buildings, the first is an offices, the second is a warehouses to rent in Spain. The question is for the warehouse, this warehouse is not conditioned and the spa

1
Wed Mar 8, 2017, 8:31 pm

Minimum HVAC equipment efficiencies

NC-2009 EAp2:Minimum Energy Performance
posted by  Ricardo Sá  on 

The project seeking LEED certification includes air-to-water heat pumps (4-pipe), that are able to produce hot and chilled water (simultaneously or separetly).

1
Wed Aug 31, 2016, 7:28 pm

Football field

NC-2009 SSc2:Development Density and Community Connectivity
posted by  Instra Ingenieros  on 

Hi, Is correct to assume that a football field can be considered a basic service inside the category "fitness center"? Thank you in advance

1
Thu Jul 13, 2017, 2:36 am

French A+ VOC certification

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  LEEDme Lorenzi  on 

Is French A+ VOC certification accepted by EQ credit 4.3 compliance?

0

pressure drop adjustment System 1

NC-2009 EAp2:Minimum Energy Performance
posted by  Francesco Passerini  on 

Can the pressure drop adjustment (e.g. for fully ducted return or for particulate filtration MERV) be applied to System 1?

1
Mon Oct 3, 2016, 2:16 pm

Occupancy hours vs. Building Operating Plan

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  Anna Korinkova  on 

My question is regarding to operating hours of the building and the Building Operating Plan (BOP).

1
Thu Apr 16, 2015, 12:45 pm

mandatory efficiency for backup system

NC-2009 EAp2:Minimum Energy Performance
posted by  Francesco Passerini  on 

Shall the mandatory efficiency of section 6.4 (Tables 6.8.1) be verified also for a chiller that works as backup system (the chilled water is provided in normal conditions by district cooling)? Be

1
Fri Jul 31, 2015, 1:26 pm

Acoustic performance: reverberation time

NC-v4 EQc9:Acoustic performance
posted by  alessandro santuari  on 

Hi, we have a project with large waiting rooms: are there specific values for "Reverberation time requirements", as there are not similar room type in the table 2 of reference guide? Thanks

1
Tue Sep 26, 2023, 2:25 pm

Wood stair

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  LEEDme Lorenzi  on 

Good morning, We have a wood stair (wooden steps covered with another wood species) that is manufactured by the millwork contractor. The scale is a custom made design.

1
Mon Jan 4, 2016, 3:53 pm

Simulation. Warehouse. Fixed high racks, occupied.

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Candice Clark   on 

For a warehouse, can I deduct the permanently fixed high racking coverage area from the gross floor area, and focus my 75% daylight coverage on the aisles and landing spaces only? I say yes.

1
Thu Mar 31, 2016, 7:41 pm