Retention pond for Rainwater Management
Warehouses-NC-v4 SSc4:Rainwater managementposted by Dick Bernadi on
Does retention pond could be use as strategy to achieve this credit?
Electric Charging Forklift
Warehouses-NC-v4 LTc8:Green vehiclesposted by Dick Bernadi on
Does electric forklift accounted to get a point?
Option 2 Trasnportation Resources - Main Logistic Hub
Warehouses-NC-v4 LTc4:Surrounding density and diverse usesposted by Dick Bernadi on
If our site are below 16 km to the main logistic hub, namely airport and freight village, does it count as two transportation resources or is it count as a single transportation resources?
Rice-Field as Previously Developed Land
Warehouses-NC-v4 LTc2:Sensitive land protectionposted by Dick Bernadi on
Does rice-fields also categorized as "previously developed land"?
LEED NC V2009 - Data Center
NC-2009 EAp2:Minimum Energy Performanceposted by SW LEE on
Our project owner would like to register a Data Center under LEED NC V2009. May I know, do anyone know how to simulate the data center?
Does all of Section 1.6 results have to be filled?
NC-2009 EAp2:Minimum Energy Performanceposted by Ivan Priatman on
Dear LEED, We are trying to achieve points in EAp2 scorecard via Building Simulation Method.
CORE area and SHELL area
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Yodi Danusastro on
How to specify the IEQc 4.1 credit area limit for CS in SHELL area? in case for tenant spaces (that is still unoccupied), or the anchor tenant that has construction in parallel.
Project that only Greenfield Exist
NC-v4 SSc2:Site development - protect or restore habitatposted by Yodi Danusastro on
HI, what if at the project site is only Greenfield?
LEED CS 2009 SSc4.3 - Option 1 Preferred Parking
CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Ruel Galve on
We have a mixed use development project in Jakarta with 6 basements.
Epoxy mortar for anchoring rebar in concrete
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Anna Okviana on
Hai, my project use epoxy glue for anchoring rebar from brick wall to column and slab in indoor area. Does it must meet LEED requirement for adhesive and sealant?