Coat area - regularly occupied?

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Eric White  on 

We have an K-6 school project which is mostly views-compliant. One issue we are having in getting above 90% views requirement is the coat area at the rear of the classroom.

1
Tue Jan 20, 2015, 1:16 pm

Manufacturer Declaration Letter

NC-2009 MRc4:Recycled Content
posted by  Rezkar Abdulmajeed  on 

We completed the design of our project in 2013 and start construction in 2014.

1
Mon May 4, 2015, 1:45 pm

right of ways adjacent to project?

ND-Plan-v4 NPDc7:Transit facilities
posted by  Ian Scott  on 

Given how a project boundary is supposed to be defined, either the project side of the right of way or the far side (non-project side) of the right-of-way, for this credit how do you deal with tran

1
Mon Nov 30, 2015, 11:13 pm

Living Wall

Retail-NC-v4 WEc4:Water metering
posted by  Joanne Sawatzky  on 

We have a CI project and are targeting this as an innovation credit. There is not outside space, but there is a living wall inside.

1
Tue Jan 17, 2017, 9:17 pm

Major Renovation prerequisites

LEED Rating System Selection
posted by  Vanessa Poirier  on 

Hi all, In the case of a Major Renovation project, are all prerequisites must be answered (in all categories) or only the ones for the categories affected by the project.

1
Tue Jan 31, 2017, 4:40 pm

LEED V4 DATA CENTER

NC-2009 MPR2:Must be a complete, permanent building or space
posted by  Caroline Vallieres  on 

There is a new data center extension to an existing building of a different use (office). The extension is accessible via a corridor. The buildings do share an electrical box.

1
Mon Dec 8, 2014, 6:21 pm

High-Volume vs. Convenience Copier 5,000 pages - CIR 872 Canada

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Lindsey Kindrat  on 

Heads up for those working on LEED Canada NC 2009 projects, CIR 872 ruled 5,000 pages per month as the definition limit for a convenience copier. Ruling provided 2012-06-08.

0

Credit Interpretation Request to support SS p1.

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Marie-France Duthilleul  on 

When comparing your proposed ESC PLan Is there standard text language / narrative that clearly describs the requirements of Phase 1 and Phase II of the NPDES program.

0

Option 2 Meaning of "Contiguous Area"

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Daniel Smith  on 

Some of the air handling units at the site (police station) where I will be conducting air testing serve more than one area on a given floor, and these areas are not directly connected to each othe

1
Mon Oct 31, 2016, 2:10 pm

green roofs

NC-v4 WEp1:Outdoor water use reduction
posted by  Geoffrey Katz  on 

Hello all, Under Option 1 are vegetated (green) roofs considered as part of the landscape that requires (or does not require) a permanent irrigation system?

1
Wed Mar 29, 2017, 3:11 pm