Post construction AND Post Occupancy Flush Out

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Denise Domino  on 

3.2 IAQ Mgmt. Plan - What are your options if neither Option 1 or 2 were done?

1
Sun Aug 27, 2017, 12:09 am

PLF4 was not approved because ..& recommendation for final submi

NC-2009 PIf4:Schedule and Overview Documents
posted by  Matt Dem  on 

Plf4 was not approved because GBCI is asking int & ext photos & renderings of the building. This was Design Preliminary submission and construction has just started.

1
Wed Jan 21, 2015, 7:34 pm

Regularily Occupied or not?

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Alex Barrera  on 

I'm working on an industrial building in Virginia. One of the rooms is a Quiet/Sleep room, where employees can rest in between their shifts.

1
Fri Jun 17, 2016, 12:29 pm

Site adjacent to 5 lane highway - with no On-0ff ramp.

Warehouses-NC-v4 LTc4:Surrounding density and diverse uses
posted by  Joyce Kelly  on 

If the Distribution center is less than 1-mile driving distance of 5 lane, wide shouldered Carlyle turnpike aka Route 11 (center lane = turning lane), does that qualify as a highway for the purpo

1
Tue Jan 17, 2017, 9:25 pm

Performance Period

EBOM-v4 WEp2:Building-level water metering
posted by  Matthew Hanks  on 

I was hoping to get some clarification about the question that was asked below. What is the performance period for this credit?

1
Tue Jun 23, 2015, 12:56 pm

EAp2 Energy Equipment form

CI-2009 EAp2:Minimum Energy Performance
posted by  Steve Zuwala  on 

When listing non-energy star equipment we enter N/A in the Make or model column.

0

Demolished Building - Material Reuse

NC-2009 MRc3:Materials Reuse
posted by  Lauren Bellamy  on 

Our client has demolished the existing structures on our site and salvaged all the cladding and flooring materials (i.e.

1
Tue Sep 22, 2015, 8:48 pm

phases of project & VOCs

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Debra a. Lombard  on 

we are a GC working on a project that is the renovation of a historic bldg and that renovation started a very long time ago '(about 3 yrs ago) and about a year before the project was registered for

0

Bake Out?

NC-v4 EQc3:Construction indoor air quality management plan
posted by  Rosemary Ziemann  on 

Hello, Is the strategy of using a "bake out" to remove VOCs from interior building materials advisable?

1
Thu May 4, 2017, 11:50 pm

supplemental heating system

CS-2009 EAp2:Minimum Energy Performance
posted by  Alfonzo Collins  on 

I am working on a high-rise residential building with VRF. The building envelope is heavily glass, so the owner has decided to also install a hydronic heating system at the building perimeter.

1
Tue Oct 28, 2014, 4:15 pm