LEED Schools or LEED CI?
Schools-NC-v4 MPR2:Must use reasonable LEED boundariesposted by Peter Doo on
We are pursuing an interior renovation of a k-12 school building to ongoing school use. Can we use LEED CI or must we use LEED Schools?
Paint Certification
NC-v4 EQc2:Low emitting materialsposted by Rai Galang on
Just want to check if Green guard certification for the paint is approved for the LEED when applying for the Credit instead of Green Seal (GS-11) certification?
Crawl Space Inquiry
NC-2009 PIf2:Project Summary Detailsposted by Sara Zoumbaris on
Should a crawl space be included in the GSF of a project if it's completely empty (not hosting any mechanical equipment?) If the crawl space DOES have mechanical equipment within it, should it be i
Submitting a Product to meet LEED Certification
posted by Jeremy Henak on
Looking at what the process is for submitting a product for LEED certification. Thanks, Jeremy
Project Building Context
NC-2009 PIf2:Project Summary Detailsposted by Deirdre Espiritu on
Where can I find guidance on what density is considered Urban or SubUrban?
Campus Projects, overlapping boundaries
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Michele Helou on
MPR Supplemental Guidance page 16 states that projects in phases may have an overlapping boundary. Let's say phase 1 included shared drive and parking and it does NOT earn SSc7.1 or SSc8.
Window coating and films
NC-v4 EQc2:Low emitting materialsposted by Edgar Arevalo on
Would window coating and films fall under Interior Paints and Coatings section for this credit, or do they not apply?
EA Credit 1 ACP (Alternative Compliance Path)
CS-2009 EAc1:Optimize Energy Performanceposted by Harry Flamm on
Can someone direct me to any supporting information that explains the use of the Alternative Compliance Path for EA Credit 1 ACP?
Master's Research Survey
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Vibha Pai on
I am conducting a survey in affiliation with University of Cincinnati for my Master's thesis which would take just 10-15 minutes of your time.
77 Olfactory Comfort
posted by Carina Clark on
If a commercial project is looking to provide a kitchen/break room, some options include a separation by negative pressurization and hallways.