Exemplary Performance

Schools-2009 EAc6:Green Power
posted by  Kevin Taterus  on 

LFS 2009 rating system - Our Owner on the project received a quote from a renewable energy provider that stated we could get three points total if we purchased 100% of the energy from renewable sou

1
Tue Jul 26, 2016, 6:26 pm

43" partitions block views and negate compliance?

EBOM-2009 IEQc2.4:Daylight and Views
posted by  Vanessa Seibert  on 

I see that there was some conversation on the views credit back in 2011.

1
Tue Dec 1, 2015, 2:29 pm

"Material Value" in LEED credit calculation

General forums
posted by  Nasim Daryaee  on 

Hi every one, I have a general question regards definition of " Material Value" .ie, my structure steel value in the manufacture is 200K and the cost I paid to my sub after fabrication ...

1
Thu Dec 31, 2015, 2:40 am

Certification agency meeting the ISO Guidelines

Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Rates
posted by  Stephanie Graham  on 

Under the requirements of qualifying certification agencies, it reads, "The certification organization follows guidelines for environmental claims and third-party oversight, including ISO/IEC Guide

0

What is the baseline assumption for this credit?

CI-v4 IPc1:Integrative process
posted by  Betty Liu  on 

Hi All, We are designing a CI v4 office space in an existing high-rise building.

1
Mon Jul 17, 2017, 2:03 pm

PIf2

NC-2009 PIf2:Project Summary Details
posted by  shaun Andriano  on 

This might be an easy one... Our PI form 2 was recently not approved following final design review.

1
Mon Jan 19, 2015, 7:14 pm

Credit Still Open?

Pilot-Credits PC12:Reduced Automobile Dependence
posted by  Rachel Bannon-Godfrey  on 

Hello! We are interested to pursue option 1 and are using LEEDv4. Is this credit still open for registration? Thanks!

0

PIf2- Project Summary Details

NC-2009 PIf2:Project Summary Details
posted by  Karly Michalowski  on 

What to do if project owner will not supply project budget?

0

MRpc69 Attainable in the New Construction Project

Pilot-Credits MRpc69:Construction and demolition waste management
posted by  Vanessa Cardona  on 

This credit was readily attainable for a new residential building located in Manhattan. Six streams were recycled by tracking waste throughout the construction phase of the project.

0

Alternative to OA airflow measurement device at Building AHU

CI-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Kristopher Baker   on 

So like many on this thread, i have a LEED CI project that is 1/3 of 1 floor and is served by the base building AHU that is outside the scope and LEED boundary of the project.

1
Tue Sep 8, 2015, 3:36 pm