Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent

Parking Capacity - Police Station

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Joe Malone  on 

Working on a new police station and trying to find a route to get SSc4.4 (LEED 2009). Anyone have any thoughts? We have public and secure parking which is for police vehicles only.

1
Tue Sep 20, 2016, 11:31 pm

VRF Systems - Option 1 of EAc1.3

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Roger Carter  on 

I am looking for some feedback on the interpretation for appropriate zoning and controls. It appears that every solar exposure must have a separate control zone.

1
Fri Jul 24, 2015, 3:19 pm

Greenguard Gold, SCS Indoor Advantage Gold?

NC-v4 EQc2:Low emitting materials
posted by  Erin Holdenried  on 

Do these certifications meet the requirements for furniture?

1
Tue Jan 17, 2017, 5:41 pm

DES Option 1 - Baseline System Heating Type Clarification

NC-2009 EAp2:Minimum Energy Performance
posted by  Mike Ramos  on 

We're using Option 1 of the "Treatment of District or Campus Thermal Energy in LEED v2 and LEED 2009 - Design and Construction" document to comply with EAp2 / EAc1.

1
Mon Nov 2, 2015, 5:59 pm

Portable Basketball Floor

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Summer Minchew  on 

Would a portable basketball floor be considered not "permanently installed" and therefore not subject to credit requirements?

1
Wed Apr 5, 2017, 4:32 pm

EBOM Solid Waste Management Policy in Medical Office Building

NC-2009 IDc1:Innovation in Design
posted by  Sara Goenner Curlee  on 

My project is pursuing LEED NC, and was hoping to use MRp2 as an innovation credit.

1
Mon Mar 13, 2017, 5:31 pm

Bus Line Rerouting for Adjacent Bridge Construction

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Kevin McNulty  on 

Hi. My firm is working on a building that will be located right at the foot of a large bridge project that is currently in construction (estimated reopening in a few years).

1
Thu Sep 14, 2017, 4:06 pm

Ability to make a design final submission

General forums
posted by  Madhura Dhayagude  on 

I am a part of this project which was registered 3 years ago with Initial review submitted.

0

SSc5.2 Project Boundary

NC-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Christopher Widdowson  on 

If we are using a portion of adjacent Conservation Area to maximize the Open Space via a permanent easement, do we include the easement area within the Project Boundary on all documentation?

1
Tue Jan 17, 2017, 11:46 pm

CFD Model

Healthcare-v2009 IEQc5:Indoor chemical and pollutant source control
posted by  ESD Engineer  on 

I'm currently working with a CFD modeler for the contaminants portion of this credit. We're having trouble finding the generation rates per square foot of active contaminant.

1
Sun Aug 27, 2017, 1:16 pm