Prefinished wood flooring

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Brianna Brandsen  on 

when installing prefinished wood flooring in a building that is attempting LEED certification, does the finish need to be compliant with LEED regulations, as you are not applying the finish on site

1
Fri Feb 10, 2017, 7:02 pm

IAQ Testing

Discuss the LEED Dynamic Plaque and Arc
posted by  Roland Jones  on 

I have been asked to provide IAQ Testing for LDP, and am having trouble finding the distinctions between the normal pre-occupancy sampling for credit 3.2 and the during occupancy sampling of LDP.

0

Hotel Occupancy

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  jupiter luner  on 

I've determined the occupancy for a hotel project we are working on based upon LEED interpretation 2706606.

1
Thu May 11, 2017, 4:48 pm

Denial of EA PR2

NC-2009 EAp2:Minimum Energy Performance
posted by  Roxanne Button  on 

A client has asked for my advice in appealing the denial of PR2. I've taken a quick look at the review comments but will be digging deeper into it in the next couple of days.

1
Fri Mar 25, 2016, 2:35 pm

Airflow measurement device serving multiple AHUs?

NC-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Mike Fortier  on 

Hello, Is it okay to install one airflow measurment device within an outdoor air intake that serves multiple AHUs or does each AHU need to have its own airflow measurement device? Thanks!

1
Mon Aug 7, 2017, 3:15 pm

Process Water Reduction

Schools-2009 WEc2:Innovative Wastewater Technologies
posted by  Charles Shinneman  on 

Can this credit be used for process water reduction? Washing machines for example.

1
Sun Aug 27, 2017, 12:13 am

Sculpture Lighting

CI-2009 EAc1.1:Optimize Energy Performance—Lighting Power
posted by  Kristopher Croghan  on 

Our client is looking at a sculpture for an LEED CI space. The sculpture is made from wire and LED lighting.

1
Thu Aug 11, 2016, 1:37 pm

LEED for Homes MidRise and Commercial Condo Space

LEED for Homes (LEED-H) Forum
posted by  Jennifer Preston  on 

First, context: We have been hired to certify a community space in the bottom 2 floors+basement of a 5-6 story Multi-Family MIDRise project.

1
Mon Jun 22, 2015, 1:39 pm

Planters

NC-v4 SSc3:Open space
posted by  Justin Halse  on 

We are working on a project for a college campus in LEED V4. We have planters on the project that we will use and I was wondering where LEED sits on that.

1
Wed Jan 18, 2017, 4:11 pm

Option 1 - how to account for a structural truss in the calcs

Schools-2009 IEQp3:Minimum Acoustical Performance
posted by  Jeremy Knoll  on 

In our classrooms and other core learning spaces, we are leaving a concrete, pan joist system exposed.

0