PI Form4 - Lease Requirement
CI-2009 PIf4:Schedule and Overview Documentsposted by Ludmilla Pavlova-Gillham on
My University (12M GSF, 13 divisions, 54 major business units, over 250 major departments), has a multi-use building (287,000) that is undergoing a commercial retail renovation on the ground floor
Can I defer any ID credit to submit it w/ construction package ?
NC-2009 IEQc7.2:Thermal Comfort—Verificationposted by Matt Dem on
Hi, I previously filed an innovation credit with my design preliminary submission and received an comment from GBCI therefore it is pending.
tenant requirements to maintain compliance with IEQc8.1 and 8.2
CS-2009 IEQc8.1:Daylight and Views—Daylightposted by Gail Napell on
Has anyone had comment from GBCI when taking these credits for a speculative C&S office building? We provide a proposed tenant layout that shows the interior complying with these credits.
shuttle bus to rail station
CI-2009 SSc3.1:Credit Alternative Transportation—Public Transportation Accessposted by Gail Napell on
we have a project with the main entrance 0.3 miles from 4 public shuttle bus stops that provide express connections to a commuter (and regional, and national!) railway station.
New to LEED Submitals
posted by Joel Clonch on
I have a mill-work submittal that requests : LEED Submittals: 1. Product Data showing VOC content does not exceed 30 g/L for wood adhesives and 80 g/L for contact adhesives. 2.
The three dimensional orientation of the luminaire
Pilot-Credits SSpc7:Light pollution reductionposted by Aly Rawji on
Can you please provide a sample for this, what is required for "The three dimensional orientation of the luminaire (plan/ elevation)"?
Implementing on a university campus
Pilot-Credits PC14:Walkable Streetsposted by Dee Spiro on
When I searched the forum for insight on how to apply/adapt some of the requirements for a campus setting, the posts were from way back in August 2012.
Cooling Towers at Central Plant
NC-v4 WEp2:Indoor water use reductionposted by Risto Beatty on
If cooling towers are located offsite at a central utility plant, does the project need to comply with the cooling tower requirements of this prerequisite?
Bus service in opposite directions
Healthcare-v4 LTc5:Access to quality transitposted by Bryan Finnegan on
The credit requires "Qualifying transit routes must have paired route service (service in opposite directions)" We have two transit routes that run within the required distance of an entry, but th
Pilot Credit 87: Verified C&D Recycling Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by David Dixon on
have several project and have had to work with the contractors and their LEED coordinator to select a company that is verified for this credit.