Forum quick links
Daylight savings time
Schools-2009 IEQc8.1:Daylight and Views—Daylightposted by James Geers on
I am assuming the daylight modeling must utilize daylight savings time. Is this correct?
EBOM v4 prereqs a barrier?
posted by Nadav Malin on
Gary--I'm interested in your experience with the College that couldn't do EBOM v4 because of the prereqs. Can you say which prereqs were the challenge?
Comms/ data room cooling - Process Energy for LEED
NC-2009 EAc1:Optimize Energy Performanceposted by Victoria Watson on
Hi all, I am working on a project where the CRAC unit manufacturers have said they don't need to comply with the efficiency requirements of ASHRAE 90.1 for a data room and comms rooms air conditio
LEED v4 delay with ACC implications..??
posted by Mark Perepelitza on
One thought that keeps coming into my mind is how this comes on the heals of the recently announced 'partnership' with ACC. My guess is that this has something to do with the delay.
Changing from LEEDv4 to LEED 2009
posted by P Fanfulik on
I registered a project under LEEDv4 (#100038645) because my anticipated completion was past the LEEDv4 sunset date.
IEQ4 credit uploads
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Shivani Langer on
We are trying to submit credits IEQ4.1, 4.2, 4.4 and 4.5 under LEED for schools version 2009.
Microturbines and gas rates for energy modeling
NC-2009 EAc1:Optimize Energy Performanceposted by Sherman Aronson on
For a high rise project the client is considering investing in micro-turbines to generate electrical power on site from natural gas.
More Info on Program is Needed
posted by Melissa Wrolstad on
There is not very much information released on the program yet, even if you speak directly with representatives of the program and drill them with pointed questions.
Press Release Location
posted by Suzanne Johnson on
I have not been able to find the referenced press release to share with clients. Please let us know where to find it. Thank you.
Should LPD Area match with Gross Project Square Footage?
CI-2009 EAc1.1:Optimize Energy Performance—Lighting Powerposted by Sunayana Jain on
I have a project in which my calculated area by space by space method is slightly more than the area inserted by LEED Admin in "Gross Project Square Footage". Should these numbers match?