Forum quick links
Fire Department Practice Burn
NC-2009 MRc2:Construction Waste Managementposted by Brian Leet on
We have a project on a large campus which has involved demolition of over a dozen buildings.
No autosizing of equipment on proposed?
NC-2009 EAp2:Minimum Energy Performanceposted by Saju Varghese on
Is there a reason why the equipment on the proposed can not be autosized?
Re-applying for a credit approved in Design submittal
posted by Shivani Langer on
At the time when we were submitting our design submittal, the elementary school project was only going to be able to get 7% of its energy offseted with renewables.
Survey for Sixth Graders
Schools-2009 IEQc7.2:Thermal Comfort—Verificationposted by Matthew Heaton on
A comment that came back on our IEQc7.2 design review asked us to "Please provide confirmation that the survey will be administered to include all building occupants, including students of grades s
Lose Leed Certification?
posted by Tim Meadows on
We have a parking deck that is LEED certified. We have several EV charging stations in employee and visitor areas.
Office Transient
NC-2009 PIf1:Minimum Program Requirementsposted by Nate Steeber on
I received some technical advice on my project regarding the occupancy. I have a mixed-use building. Primarily office spaces with a tenant fit out cafe and restaurant.
VOC Compliant Chemicals - IEQ3.3
EBOM-2009 IEQc3.3:Green Cleaning—Purchase of Sustainable Cleaning Products and Materialsposted by Jessica Wasmuth on
I am working on compiling a list of our Green Chemicals used onsite for a LEED certification.
Addition added after documentation has been submitted
NC-2009 MPR2:Must be a complete, permanent building or spaceposted by Angela Bickford on
I think I know this answer to this, but I can't find an answer anywhere so I would like someone else's opinion. I'm working on a LEED for schools project. About 3/4 of the building was renovated.
LEED final review...past due?
posted by John Stouffer on
Is LEED final review typically late? The anticipated date of return was 10 days ago. We're getting a little nervous. We did have a clarification, but that was returned in a timely manner.