Equipment Efficiency Section 1.4

This section is a little confusing and I am putting my interpretation of it up. Please let me know if I am correct. Total Project Space Load (heating/cooling): I did load calculations for the entire building and put the peak space load here. Total Project Space Equipment Capacity (heating/cooling): I added up all of the installed or designed equipment capacities here. Total tenant space fan and pump sizing: I have no interpretation for this. In need of help.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 09/19/2012 - 15:35

For "fan and pump sizing" we add up the total fan and pump capacity within the project scope (kW or hp).