NC-2009 MPR6:Must commit to sharing whole-building energy and water usage data

MPR #6 modification

Hello, I've seen in leedonline for a recently registered project I'm working on that this form (PIf1) has been updated from version 4.0 to 5.0. In the version 5.0, there is no longer the option to use the Energy Star Portfolio Manager to get an Exemplary Performance. So, can the projects that have been registered before this change still be applying for this Exemplary Performance Point (EAc5.1)? To sum up, I think this change just applies for projects that are registered after the change, right? Thanks in advance.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 11/05/2013 - 13:57

Yes, with any change of this nature it applies to projects registered after the date it took effect.