Energy Model Calibration by Post Construction data
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Gabriela Hernández Castillo on
Our Project is applying for M&V plan option D method 2, which let us calibrate the energy model with post construction measures.
Sub Metering of Service Hot Water (Domestic Hot Water)
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
Does Service hot water need to be sub-metered to satisfy this credit ? If not will it make the energy model more difficult to calibrate.
Tenant Submetering connected to BMS?
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Marco Abdallah on
We are pursueing 5.1 Opt. 1 and 5.2 at a CS-project with 10 floors leasable to different tenants.
Separating lighting metering from plug load metering.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Rudolph Carneiro on
I have seen many comments in this forum stating that plug loads should be metered seperately from lighting loads. I'm not sure if seperating these loads is actually necessary.
Model Calibration - Margins for Error
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
For a new office building would it be acceptable to use these error margins for an M&V Report.
EA Credit 5.1: Base Building Sub-metering
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ian McCall on
Hello all, I am working on a large Core and Sheel project composed of office spaces and commercial centre (in France). The comercial centre is 5 stories high and occupied by one single tenant.
EAc5.1 Review Report Help
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Redy Truccolo on
Hi, I received these technical advices but I don't really understand what they're asking me to add to the M&V Plan: 1.
Speculative Retail - No Meters Provided.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
Im working on a mixed use development that consists of office space and retail units.
Emergency Power
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Brightworks Sustainability on
The engineer on my project is asking what exactly needs to be submetered and I'm having difficulty answering just because I'm not as familiar with the credit details.