What are the requirements for the inspectors?
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Jose Gonzalez on
We are completing a high-rise in Surfside, FL and we fall under the jurisdiction of FDOT, FDEP, and the EPA as this is a Beach side construction.
The most stringent rate for vehicles
Schools-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by milton muñiz on
I chose option 1 of SSC4 but the building is Located in Guadalajara Mex.
Mixed Use Residential Baseline 90.1-2004
NC-2009 EAc1:Optimize Energy Performanceposted by Ruben Porter on
*Moved to NCv2.2 Credit EAp2
Historical data with building and tenant changes
EBOM-2009 IOc3:Documenting sustainable building cost impactsposted by Tiffany Moore on
I'm trying to clarify how or what to provide in terms of historical data for an O+M project with a performance period that will begin at day 1 of occupancy in an NC project.
Chilled Water Pumps, Primary/Secondary
NC-2009 EAp2:Minimum Energy Performanceposted by Aaron Dahlstrom on
ASHRAE 90.1-2007 Sec G3.1.3.10 requests that users specify pump power of 22 W/gpm, with a primary / secondary pumping system and variable flow on the secondary side.
RAVOCs
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Eduardo Guzman on
Our contractor would like to use a flat pain that gives both a VOC content measurement and a RAVOC content measurement.
Floodlight
NC-2009 EAp2:Minimum Energy Performanceposted by Ameet AA on
2. Lighting requirement from ASHRAE 90.1-2007 Appendix G?
Can I use CONTROL as an energy saving strategy??
CS-2009 EAp2:Minimum Energy Performanceposted by Esteban Undurraga on
Dear all: We have an specific question related to the Whole Building Simulation of an office Building. The electricity distribution company established a maximum limit of energy use for the buil
Detailed Plant Simulation
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Chilufya Lombe on
Hi, we have a project with a certain number of 'back up' systems for air conditioning.
Can the Technical Controller on the project be the CxA as well?
NC-2009 EAc3:Enhanced Commissioningposted by Maya Karkour on
Hello, We are working on a project which seeks to achieve EA c3.