Implementing the M&V Plan
NC-2009 EAc5:Measurement and Verificationposted by Eamon Geary on
I have a project seeking this credit where our MEP subconsultant is writing the M&V Plan and the Owner is implementing the M&V Plan.
Baseline External Lighting Calc
NC-2009 EAp2:Minimum Energy Performanceposted by Jean Marais on
I'm using Revised Section 1.4 Tables (October 2012).
Detail on "green vehicles"
Pilot-Credits LTpc70:Green vehiclesposted by Kath Williams on
For this credit achievement, there has been project team discussion about details required. Company only uses electric vehicles on campus.
Happy Holidays and Many Thanks...
Healthcare-v2009 MRc3:Sustainably sourced materials and productsposted by Catherine Blakemore on
Just want to wish everyone Happy Holidays and the best wishes for a fabulous 2014! Also many thanks to everyone who gives of their time to help us all. We greatly appreciate it.
Preassure drop adjustment
NC-2009 EAc1:Optimize Energy Performanceposted by Jorge Lopez de Obeso on
Hello everyone, we are working on a laboratory and we have very restrictive filtering in some spaces there are equipments that have MERV 7 + MERV 13 + MERV16 filtering sections. In the ASHRAE preas
SSpc16 - Rainwater Management
Pilot-Credits SSpc16:Rainwater managementposted by Joseph Haupt on
There are local/regional requirements that may be more applicable, but it is not apparent how local/regional requirements could be included in this credit.
Previously developed major renovation
NC-2009 SSc1:Site Selectionposted by LEED Pro Consultant on
Hello, my question is regarding an existing industrial plant that went under major renovation of the building, process, etc. The site is obviously previously developed, since it has a building, roa
Planned Off-site Parking Spaces
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Weidong Luo on
We have a project with no on-site parking and come up with "No New Parking" for SSc4.4.
natural ventilation design in hot and humid area
NC-2009 IEQp1:Minimum IAQ Performanceposted by Jorng-ren Chern on
My project is a high rise residential building located in a hot and humid area.
Handicapped toilet and Pedal-type toilet flush valve
CI-2009 WEp1:Water Use Reduction—20% Reductionposted by Shirley Li on
Hi all, We are working on a renovation office project, with fixtures located outside of tenant space. There are 2 restrooms loacated at public core area, one for Female, another one for Male.